On July 1st and 2nd The Society attended the Hearings on PL11 (Crews Hill). The first day we had to endure the heatwave with the Council’s failed air-con, and a marathon second day which over-ran by 1h 15m in order to prevent spilling into a third.
You must have sympathy for Mr Steven Lee, the Inspector, who has had to read thousands of pages of evidence submitted by both the Council and objectors.
The Hearings take the form of questions which have been published in advance. Its clear from his questions to the Council that the Inspector has indeed read a great deal and understands the Plan. The questions are designed to test the ‘soundness’ of the proposals and their conformity with National Planning Policy. What is evident from the Hearings is that there is no one person among the Council staff who understands the whole Plan; different staff or consultants employed by the Council (and there are a lot of them) come to the table at different times. Throughout the Council is represented by a barrister, Mr Reed KC. Whilst hearings are not a judicial process, the outcomes can be subjected to a judicial review if one of the parties is not satisfied with the outcome.

Green Belt Boundaries
The Council are proposing to remove all of Crews Hill from the Green Belt. The new boundary is being proposed along East Lodge Lane and Cattlegate Road to the west, the M25 to the north and to the east of Theobolds Park Road.
We have argued that the new proposed boundaries in the west are significantly weaker than if the railway line were used. The new boundary to the east is also weak in places. Our concern is that weak boundaries will not resist the pressure to extend the Green Belt in the future.
The Inspector also noticed that there are large pockets of land being removed from the Green Belt where the Council currently have no stated plans. These are referred to as “white space”. The concern is that once removed from the Green Belt there will be nothing stopping a planning application coming forward on these sites.
Perhaps the most significant of these is Kings Oak Plain between the golf course and Rectory Farm. Though the Council argued in Hearing that there were no plans for development, we pointed out that the Council’s own property team have promoted this site for housing. Though the Inspector is careful not to convey his views at this stage, we felt that he appreciates the issue.
It’s a similar story with the golf course where there is a proposal for 200 homes on the north of the site. Without modifications to the policy, development will be very difficult to stop spreading southward over the highly important bio-diverse rich acid grassland of the course.
Another major concern for The Society is the impact of the development on distant views across the landscape from places such The Ridgeway. The Society presented detailed modelling by landscape experts, notably missing from the Council’s evidence, showing the scale of visibility even from development to the east of the railway. This is show below. Purple shading is where the development will be visible from.

Compensatory Improvements
If Green Belt is released then improvements to the remaining Green Belt must form part of the proposals. With the Local Plan the Council have a number of schemes included in the Plan, mainly in policy BG7. However the majority of these have already been funded and completed as part of the Enfield Chase Restoration work. The Inspector must decide for himself to what degree the remaining and unfunded work can be considered sufficient compensation.
Supplementary Planning Document
The Hearings were examining policy PL11. An important aspect is that a more detailed plan will be created after the Plan is approved, called a Supplementary Planning Document (SPD). Whilst it is normal to create such a document, the issue with Crews Hill is that there appears to be an abnormally high amount of decisions being deferred to the SPD, which makes evaluating the plans harder at this stage. One example is the location of three new schools being proposed, where although the current plans show ‘indicative’ locations, the final details will be in the SPD.
The Council confirmed that they are working on the SPD now and that it is proposed to go the the November 2025 Cabinet for approval and then public consultation. But, of course, this is dependent on the Inspector’s findings.
Delivery and phasing
The development of Crews Hill is a long-term project. It is intended to eventually deliver about 5,500 homes, with about 3,500 up to 2041. Phasing the delivery was an important question for the Hearings. Berkeley Homes confirmed that their proposals for land between Cattlegate Road and the M25 (SA11.1) are at an advanced stage. It was anticipated that 650 homes could be built on the site, though the Council argued the capacity is higher at 800. Work could start between 2028–30. This would be the first site to be developed.
There is a considerable amount of brownfield at Crews Hill with many land-owners. Some are not minded to take part in the project. This is in the ‘core area’ around the current garden centres. Here development will obviously be slower and it may also require the Council to use Compulsory Purchase Orders (CPO) to ensure land is available. This is expensive.
When questioned about CPO, Mr Reed explained that there was a Crews Hill Stakeholders Forum which was trying to reach agreement between the landowners so that CPO was a last resort—’a back-stop’. The Inspector asked if the Council had the necessary funds for CPO, but Mr Reed said he would need to seek that information.
If the site as proposed by the Council were approved by the Inspector, the immediate availability of land in the Green Belt and the difficulty of assembling land-owners in the core of the site, would combine to create irresistible pressure for building on the Green Belt “white space” identified.
What might happen?
It is impossible to know what the Inspector will decide. The GLA and TfL have in-principle objections to the whole site, saying it is not sustainable because it has too few houses and a too lower density to justify the new bus services needed. The Council’s argument is that the Inspector needs to consider the consequences of rejecting the site as this will affect its ability to deliver the housing needed by the Borough.
Then the Inspector may decide to make so-called modifications, changing the proposals to make it ‘sound’. This might include reducing the size of the site to limit the harm to the Green Belt and protect those areas removed but without current proposals—like Kings Oak Plain.
Given the way Crews Hill has been allowed to develop in the past, despite it being largely in the Green Belt, it looks like it will be very difficult to resist some development from taken place to the east of the railway. An important consideration here is the new National Planning Policy Framework (NPPF) which came into effect in 2024 and recognised ‘grey belt’ (low value Green Belt) as potential development area. Even though this Examination is under the 2023 NPPF, future plans—including the London Green Belt review now underway—will take account of this.
You might also like to reach the thorough report in The Enfield Dispatch.